Projects underway by NHAI & State R&B (NH) in Gujarat; Status as on 19 January 2023
January 19, 2023
Gandhinagar: During the visit of union minister for Roads and Transport Nitin Gadkari in Gujarat, the ministry has shared a note titled as ‘Brief for projects being implemented by NHAI & State R&B (NH) In the State of Gujarat Status as on date 19th January 2023′. Presented below is the note in full text:
Since its independence, India has made tremendous progress across various sectors including infrastructure and it’s no surprise that we have grown to become the world’s fifth-largest economy.
The infrastructure sector is the cornerstone of the Indian economy. Being one of the most resilient sectors, it has played a crucial role in accelerating India’s overall development. Today, India has one of the world’s largest road networks and we are among the fastest developers of highways in the world.
India is giving high priority to the development of its highway infrastructure. From Greenfield expressways and smart highways and to all-weather tunnels and mega bridges, India’s highway infrastructure is truly becoming world-class.
Led by the Ministry of Road Transport & Highways, NHAI is working tirelessly towards realising the Government’s vision of holistic infrastructure development and enabling easier interconnectivity between road, rail, air, and waterways.
Ahmedabad-Dholera Expressway
Brief:
NHAI has taken up the work of development of 04 lane Ahmedabad – Dholera Greenfield Expressway having total length 109.019 km on the request of Delhi Mumbai Industrial Corridor Development Corporation (DMICDC) which primarily caters to the Special Investment Region coming up at Dholera. The project is taking off from Ch. 0+000 at Sardar Patel ring road near Village Visalpur in Ahmedabad District and ending at Ch. 109+019 after Dholera Special Investment Region (DSIR) near Adhelai Village in Bhavnagar District. This 109.019 km long expressway is taken up under 04 packages and brief details are as follows:
| Package | Contractor
|
Length (in km) | Appointed date | Present Physical
Progress |
Target Completion Date | |
| Package-I | M/s Sadbhav Engineering Ltd. | 22.000 | 11.01.2022 | 21.40% | 31.03.2024 | |
| Package-II | M/s Sadbhav Engineering Ltd. | 26.520 | 21.01.2022 | 11.70% | 31.03.2024 | |
| Package-III | M/s GHV (India) Pvt. Ltd. | 22.540 | 19.07.2021 | 22.50% | 31.03.2024 | |
| Package-IV | M/s Dineshchandra R Agrawal Infracon Pvt Ltd- MKC Infrastructure Ltd (JV) | 37.959 | 13.12.2021 | 28.19% | 31.03.2024 |
- The expressway will be a lifeline for the Dholera Special Investment Region (DSIR) and develop direct connectivity to coastal highway. The proposed corridor will pass through the Ahmedabad and Bhavnagar Districts of Gujarat State and will provide direct connectivity to DSIR from Ahmedabad and Bhavnagar. Thus, the expressway will leave no stone unturned for socio economic development of this area.
- Present distance to reach Dholera from Sardar Patel Ring Road (SPRR), Ahmedabad is 100 km and travel time is 2hrs:15min which will be reduced to 83km and 45min respectively after construction of expressway. Similarly, Distance to reach Bhavnagar from SPRR, Ahmedabad will reduce from 169km to 141km and travel time will reduce from 3Hrs:15min to 1Hrs:45min.
- 4-lane access-controlled Ahmedabad – Dholera Expressway is proposed to be implemented under EPC mode at a total capital cost of Rs.4,110 Cr. It shall have closed tolling arrangements. Further, 26m median is proposed to accommodate future 08 lane widening in inner side.
- 02 nos. Wayside amenities of World class level are planned across the expressway at intervals of about 50 km on either side to improve rider comfort and to enable safer travel.
- 20 Lakh Metric Ton of Ahmedabad Municipal Corporation waste material and 25 Lakh Metric Ton of Pond Ash generated from Power Plant is being used as substitute of earth/soil as filling material that will help in conservation of minor mineral (soil) and disposal of harmful waste thereby leading to environment conservation along with boosting of innovative technology.
Summary of Expressway being constructed/ Planned in the State of Gujarat are as under:-
| Expressways (NHAI) | |||||||
| Sr No | Section | Current Project Stage | Length
(In Km) |
Cost
(In Cr) |
Length Completed Till Date | Balance Length | Expenditure till date (Cr) |
| 1 | Delhi-Mumbai Expressway
(16 Pkgs) |
Under Implementation | 423.21 | 32092.00 | 126.21 Km | 297 Km | 13,747.50 |
| 2 | Ahmedabad-Dholera Expressway
(4 Pkgs) |
Under Implementation | 109.10 | 4,110.00 | 0 | 109.09 Km | 1459.85 |
| 3 | Amritsar – Jamnagar Expressway
(4 Pkgs) |
Under Implementation | 125.00 | 2964.58 | 94.42 Km | 30.58 Km | 1938.08 |
| 4 | Tharad –Ahmedabad
(5 Pkgs) |
DPR | 213.80 | 6200.00 | – | – | – |
| Total | 871.11 | 45366.58 | 220.63 | 436.67 | 17,145.43 | ||
- National Highways network
- Expansion of NH network: The total NH network is the State of Gujarat was 3946 km until 2014. The NH network has been expanded to 7283 km by adding 3337 km to the NH network in the State of Gujarat during last 8 years i.e growth of 84.57 % in the NH network in the State of Gujarat in last 8 years.
- Connecting all Districts with NH: All 33 districts in the State of Gujarat now have connectivity to a robust network of National Highways. The NH network density in Gujarat now is 36.93 km/ 1000 sq km against National average of 39.90 km/1000 sq km. The population density of NH network in Gujarat is 12 km / Lakh population against national average of 10.80 km / Lakh population.
- Development and improvement of National Highways in the State of Gujarat
- Sanction of new works for development of National Highways: For development and improvement of National Highways, 81 nos. of works of total length 1976 km with total cost of Rs.52,775 Cr have been approved in last 8 years. This includes 657 km length of Expressways. In addition to these works another 22 works are in planning stage which will cover 1366 Kms of NH stretch at a cost of Rs.30,908 Crs. With this approximately Rs.1,08,690 Cr are being spend for Construction and Improvement of National Highways in the State of Gujarat.
List of approved / sanctioned works since 2014-15 to till date
| Sr. No. | Name of work | TPC
[Rs Cr] |
Length
(km) |
| 1 | Delhi-Vadodara Eight Lane Expressways (6 Packages in Gujarat State) | 8485 | 149 |
| 2 | Vadodara to Mumbai Eight Lane Expressways (10 Packages in Gujarat State) | 20116 | 275 |
| 3 | Ahmedabad-Dholera Expressways (4 Packages) | 4929 | 109 |
| 4 | Sanchore to Santhalpur Expressways (4 Packages) | 2965 | 125 |
| 5 | Bhavnagar to Dwarka section of NH-51 (8 Packages) | 6043 | 467 |
| 6 | Naroda – Chiloda – Shamlaji section of NH-48 | 1608 | 109 |
| 7 | Left out of Jetpur-Somnath including Junagadh bypass NH-27 | 232 | 19.80 |
| 8 | Gondal Chokdi Flyover at Rajkot | 90 | 1.50 |
| 9 | Deesa Elevated Corridor | 194.25 | 3.50 |
| 10 | Dholera end to Nari – section of NH-51 | 820 | 33.30 |
| 11 | Dwarka (Kuranga)-Khambhaliya-Devariya section of NH-151A | 1024 | 66.89 |
| 12 | Dhrol-Bhadra-Patiya and Bhadra Patiya-Pipaliya | 896.97 | 50.4 |
| 13 | Upgradation to 4L PS from Bhimasar, Junction of NH-41 to Anjar- Bhuj up to Airport Junction from Km 0.000 to Km 65.478 of NH-341 | 1373.06 | 59.75 |
| 14 | 4L PS Divided Carriageway from Patan (Near Rajpur) to Gojariya From Km 52.000 to Km 128.940 of NH-68 | 1181.34 | 76.94 |
| 15 | Widening to 6L of Existing 4L Jetpur-Gondal-Rajkot Section from Km. 117.600 to Km. 185.00 on NH-27 | 2070.44 | 67.4 |
| 16 | Construction of Signature Bridge between Dwarka & bey Dwarka and its approaches in the State of Gujarat on EPC Mode [NH-51/Gujarat(02) 17-20-S & R (B)] | 962.42 | 5 |
| 17 | Development of Chiloda – Gandhinagar- Sarkhej ofNH-147 (old NH-8C) Package- I Ch. 0.0 to 16.290 Km | 164.64 | 16.35 |
| 18 | Development of Chiloda – Gandhinagar- Sarkhej ofNH-147 Package -II | 211.28 | 14.95 |
| 19 | Development of Chiloda – Gandhinagar- Sarkhej ofNH-147 Package – III | 322.58 | 4.18 |
| 20 | Development of Chiloda – Gandhinagar- Sarkhej ofNH-147 (old NH-8C) Package- IV Ch.35.430 to 44.420 | 147.52 | 9 |
| 21 | Up gradation of newly declared NH-341 to two-lane with Paved shoulder configuration between Km. 65.478 to Km 162.209 ( Bhuj Airport Jn – Khavda – India Bridge to Dharmshala section) in the State of Gujarat . | 351.54 | 96.7 |
| 22 | Construction of Missing links (single lane) in Lakhpat- Gaduli-Hajipir-Odma-Khavda-Dholavira-Mauvana-Gadkabet-Santalpur road along the Indo-Pakistan Boarder in the State of Gujarat (Newly declared National Highway No. 754K) | 400.76 | 79.6 |
| 23 | Widening from existing 2 lane to 4 lane including geometric improvemnet and reconstruction of existing between km.56/620 to km . 61/520 on NH- 58 in the state of Gujarat | 19.26 | 4.9 |
| 24 | Construction of Proposed ROB and its approaches in replacement of existing LC. No 3 X at km 88.565 of NH -64 District -Anand in the state of Gujarat | 70.96 | 1 Nos |
| 25 | Construction of Proposed ROB and its approaches in replacement of existing Level Crossing No.88at Km 113. (Railways ch.56/522) of NH -64(old NH-228) in in the state of Gujarat | 21.41 | 1 Nos |
| 26 | Construction of ROB with approaches on NH-848-B at Karambeli Railway Crossing L.C.No.77 @ Km 0/0 to 0/600 | 112.16 | 1 Nos |
| 27 | Construction of ROB with Approaches in lieu of L.C.No.165 of Ahmedabad-Palanpur (IR Ch-650/2-3) between Railway Station-Karjoda & Palanpur NH-58 | 166.21 | 1 Nos |
| 28 | Construction of ROB in lieu of Existing LC no. 87 along with Approach at km 28/400 to 28/600 on NH 848B at Udvada in the state of Gujarat | 37.04 | 1 Nos |
| 29 | Widening of Existing 2 lane to 4 lane with service road between Km 329/600 to 334/100 on NH-68 in the state of Gujarat | 39.74 | 4.5 |
| 30 | Strengthening of existing road between Km 33/600 to Km 55/400 [excluding Km 39/320 to Km 40/190] (Thavar-Zerda Section) on NH-168A in the state of Gujarat under EPC mode of contract. | 14.69 | 20.93 |
| 31 | Work of Installation of Crash barrier and other road safety equipments in selected stretch of NH-953 from km 22/850 to 94/600(Bardipada-Ahwa-Galkund-Shamgahan section) in State of Gujarat.( Job No.NH-953/GJ/2020-21/RSCE/016) | 8.6 | 1 Nos |
| 32 | Road Safety measures based on Detailed Road safety audit on the stretche of National Highaway from km 0/0 to Km 37/400 on N.H. -848 in the State of Gujarat. | 4.84 | 1 Nos |
| 33 | “Work of IRQP from Km 0/0 to 43/00 on NH-756 (Bodeli-Shivrajpur- Jhabughoda-Chapaner bypass section) in the state of Gujarat” | 44.32 | 43 |
| 34 | Work of IRQP between Km 377/305 to Km388/000, Km. 407/000 to Km 418/305, Km 421/205 to Km 429/405, Km 441/00 to Km 443/00, Km 444/00 to Km 445/00 & Km 449/00 to Km 452/00 Section Ferkuva-Chhotaudepur-Bodeli-Naswadi Road of NH-56 | 32.22 | 36.2 |
| 35 | ” Construction of Mandvi bypass road starting from Km. 97/200 & ending of Km. 104/ 200 of NH-8A (Extn), in the state of Gujarat “ | 62.88 | 6.1 |
| 36 | Work of IRQP from Km 16/930 to Km 21/030(Nadiad bypass section) of NH-848K in the state of Gujarat | 4.28 | 4.1 |
| 37 | Widening and Strengthening of existing carriageway from Km 265/200 to 266/200 and 273/00 to 287/905 on NH-56 uin the state of Gujarat | 34.24 | 15.91 |
| 38 | “Work of long term road safety measures for 2 Nos of Black Sport identified on NH-56 from Km. 378/00 to Km. 379/00 in the state of Gujarat. “ | 2.46 | 1 Nos |
| 39 | Work of rehabilitation of Major bridge on Saraswati River at Km. 133/300 and on Umarshi Bridge at Km. 153/350 on NH-58 , in the state of Gujarat. | 4.65 | 1 Nos |
| 40 | IRQP from Km 34/480 to 74/0 of NH51 Under NH Division Rajkot Road and Building Department , Gujarat in the state of Gujarat for the year 2021-22 | 52.84 | 39.52 |
| 41 | Work of widening of road to 4-lane from Km 710/600 to Km 718/500 of NH-56 in the state of Gujarat | 53.83 | 7.9 |
| 42 | Work of construction of 1 no. of Minor bridge in place of old and narrow bridge on Kadrama Khadi between km 280/00 to 280/200 of NH-64 in the State of Gujarat | 8.56 | 1 Nos |
| 43 | work of Reconstruction of 2 nos. of bridge across river Kosh (km 634/400-600) and Kavero (km 637/800-638/00) in lieu of old, narrow and weak bridges and re-construction of 8 No. of Box Culvert Between km.585/00 to 629/400 on NH-56 in the State of Gujarat | 19.38 | 1 Nos |
| 44 | Work of IRQP from Km 65/00 to Km 77/900 for NH -351K in the state of Gujarat | 5.76 | 12.9 |
| 45 | Work of IRQP from Km 0/00 to Km 28/200 for NH -351G in the state of Gujarat | 14.48 | 28.2 |
| 46 | Strengthening/ IRQP between km 63 to km 78 of NH 351-G | 10.18 | 14.98 |
| 47 | ” Construction of new two lane bridge along with approaches across River Rudramata at Km. 75/550 on NH-341 upstream of existing bridge in the state of Gujarat “ | 13.16 | 1 Nos |
| 48 | Work of Road Safety between Km.147/4 to Km.173/2 on NH 351 in the State of Gujarat. | 1.24 | 1 Nos |
| 49 | Permanent rectification of blackspot on NH 64(Jetalpur-Bareja section) from Km 24/800 to 26/00 in the state of Gujarat | 4.96 | 1 Nos |
| 50 | Work of strenthening of between km 0/00 to km 11/500 of NH 58 | 4.97 | 11.5 |
| Total | 55458.12 Cr | 2089.9 Km | |
- Completed works of National Highway:
Construction works in 3064 km length of National Highways have already been completed during last 8 years at cost of Rs.25,007 Cr
- Major Projects in DPR stage: There are 22 nos. of work on NHs with total length 1366 km and total cost Rs. 30,908 Crore under various stages of DPR preparation.
List of projects under DPR during 2022-23
| Sr. No. | Name of work | NH No. | Approx TPC [Rs. Cr.] | Length (km) | Remarks |
| 1 | 4 laning from Dahod (on Delhi Mumbai Expressway) to Bodeli section of NH-56 and Bodeli-Netrang – Vanasda Vapi section of NH 56. | NH-56 | 9773 | 337 | Bharatmala |
| 2 | 6/8 lane Green Field Expressways from Sanchore to Ahmedabad | – | 6191.5 | 213.5 | Bharatmala |
| 3 | 6 laning of Santhalpur-Samakhiyali | NH-27 | 2639 | 91.00 | Bharatmala |
| 4 | Madhavpur to Maliya Hatina Greenfield Project | NH-51 | 894 | 30.00 | Bharatmala |
| 5 | Navlakhi Port to Morbi | – | 1189 | 41.00 | Bharatmala |
| 6 | Dwarka – Okha | NH-51 | 783 | 27.00 | Bharatmala |
| 7 | Maliya-Pipaliya | NH-151A | 552 | 18.00 | Bharatmala |
| 8 | Radhanpur-patan (2L PS) | NH-68 | 2001 | 69 | |
| 9 | Gozariya – Prantij (2L PS) | NH-68 | 1682 | 58 | |
| 10 | Dhanera Bypass (4L) | 168 | 688.17 | 23.73 | |
| 11 | Netrang – Dediapada (4L) | 753B | 1682 | 58 | |
| 12 | 4-lane from KM 92/320 to Km 115/320 (Vav Chokdi-Satlasana to to Vrundavan Chokdi, Kheralu) on NH-58 in the State of Gujarat. | 155.94 | 23 | ||
| 13 | Up-gradation of Dhoraji-Jamkandorna-Kalavad Section of NH-927D from Design Chainage km 0/00 to km 58/115 to Two lane with PS configuration in the State of Gujarat on EPC | 246.6 | 58.115 | ||
| 14 | Upgradation to 2 lane with PS from km 95/500 to 129/775(Badoli to Shamlaji section) on NH 168G | 272.7 | 35.2 | ||
| 15 | Work of upgradation of NH-351 to two lane with paved shoulder configuration (Pkg-I) (Mahua to Bhahdhada Section) | 173.06 | 47 | ||
| 16 | 2 Laning of Amreli – Bhahdhada section of NH-351 | 235 | 51 | ||
| 17 | 2 Laning of Limbdi – Dhrangadhra of NH-51 | 360 | 42 | ||
| 18 | 2 Laning of Songadh – Ahwa – MH / GJ border-(P-1) of NH-953 | 253.6 | 22 | ||
| 19 | 2 Laning of Jetpur – Amreli section of NH-351 | 274.3 | 44 | ||
| 20 | Construction of Jetpur & Vadia Bypass of NH-351 | 190.4 | 20 | ||
| 21 | Construction of Dharangadhra & Surendranagar Bypass of NH-51 | 298 | 20 | ||
| 22 | 2 Laning of Pardi – Kaprada section of NH-848 | 374 | 37.4 | ||
| Total | 30,908.27 Cr | 1365.945 Km |
DeshGujarat
🗃️ This story is from our archives and may contain outdated information.
Recent Stories
- Gujarat govt arm GIL to Deploy 100+ GPUs to Accelerate AI Infrastructure
- BJP appoints Guardian and Incharge for Umreth Assembly bypoll
- Rajkot Airport Gets Yatri Udan Cafe, Flybrary and Kids Zone
- PM Narendra Modi’s diplomacy a global garba: Actress Twinkle Khanna’s viral witty post
- 118 community kitchens operational in Surat region; Sanghavi reviews gas supply, workers arrangements
